The engine build continues to make progress although at a slower pace after the initial burst of work. The cylinders are fitted as far as can be achieved. Initial fit cannot be completed until we have the Bogie Centre Pin casting.
The locomotive build is making steady progress. Components are being permanently fitted including Cylinders, Stretchers, Motion Brackets and various other parts for Brakes and Springs.
Good progress continues to be made with the engine build. Importantly we have witnessed a good degree of continuity of work with multiple tasks ongoing.
The rear cylinder covers have been cast and have passed their testing. Machining of the covers is currently in progress.
Work on The Unknown Warrior has continued over the period since the last report. Significant progress is being made on the documentation and project planning to ensure we have captured all the work being done and compiling all the required documentation.
Work on The Unknown Warrior has continued over the period since the last report. It is very pleasing to be able to report physical progress towards the re-assembly of the chassis.
As the regulations surrounding Covid have relaxed work on The Unknown Warrior has started to return to a more normal pace. Staffing levels at the PRCLT workshops have returned to pre-Covid levels, allowing more work to be undertaken. Added to this the overhaul of 6233 Duchess of Sutherland has been completed and the locomotive has returned to service hauling trains on the national network, both on its planned commitments and standing in successfully for another locomotive.
Work on The Unknown Warrior has continued at various location since the last report.
Construction of 5551 continues at a number of locations.
Physical work on 5551 has been very slow since the last report as can be expected due to the onset of the Coronavirus pandemic outbreak. Virtually all our suppliers have had to close down or if they are still open they are working with reduced staffing levels and only working on safety critical or key work projects. Unfortunately for us, whatever we think of 5551 we do not fit into these categories!
Since the last Engineering report review we finally gained access to the former Boiler Shop at Crewe Heritage Centre which enabled us to vacate the Main Hall area which we had occupied since arrival at Crewe back in October 2018. The actual moving date was 18th April 2019 just prior to the Easter Bank Holiday.